Check epic progress in Jira with Rovo
To check epic progress in Jira with Rovo, ask an agent that reads a rollup through every level of the epic, not just its direct children: “How far along is PROJ-12?” should count the stories and the sub-tasks under them. Jira’s own epic progress counts only direct children by status, so an epic with five “Done” stories and twenty open sub-tasks can look finished. The shortcut is Tally: it rolls status and % done up through every level and ships a Tally Progress Rovo agent that answers per epic, across a JQL, and for late epics, on the free plan. Here’s how, and what each answer means.
What does Rovo need?
Rovo is Atlassian’s AI assistant inside Jira and Confluence: open Chat in the navigation bar and ask in plain language. Apps can add agents whose actions return real data from the app.
Atlassian includes Rovo credits in all paid Jira and Confluence Cloud subscriptions: Standard, Premium and Enterprise (Atlassian: How Rovo credits work). Free plans don’t include it, and chats use credits from your plan’s allowance. No Chat button? Ask your site admin.
Why isn’t Jira’s epic progress enough for Rovo?
Jira shows an epic’s progress from its direct child issues grouped by status category. That leaves out:
- Sub-tasks. Work broken down under a story isn’t counted against the epic.
- Deeper levels. On plans with levels above epic, progress doesn’t roll up through all of them.
- A stored number. There’s no “% done” field Rovo or JQL can read, so ranking epics by progress isn’t possible natively.
Rovo could open each child and try to count, but you’d have no way to check the result. For the manual method, see how to see percent complete on a Jira epic.
How do you ask Rovo with Tally?
- Install Tally from the Atlassian Marketplace. There’s nothing to configure. A background rebuild stores a rollup on every issue that has children, so existing epics are covered.
- Open the agent. Open Chat in the Jira navigation bar, choose Agents and search for Tally Progress (Atlassian: Browse Rovo agents).
- Ask. The agent picks the right action:
| You ask | What you get | Plan |
|---|---|---|
| “How far along is PROJ-12?” | % done and done / in progress / to do through every level | Free |
| “Which epics in project PROJ are least done?” | Parents ranked by % done, for the JQL Rovo writes from your words | Free |
| “Which epics are late?” | Epics past their due date that aren’t done | Free |
| “Which epics are at risk?” | Also epics whose children are due after the epic | Standard |
| “How many story points are left on PROJ-12?” | Story points and time rolled up | Standard |
- Check it on the issue. The numbers match the Tally — Rollup panel on the epic, which shows the same counts and a To do / In progress / Done bar for the whole tree.
Limits worth knowing: counts only include issues you can see. Very large hierarchies can be partial, and the agent says so when a result is capped. Story points come from the Story Points (company-managed) or Story point estimate (team-managed) field, on Standard.
What should you ask in a planning meeting?
- “Which epics in PROJ are least done?” Start the review with the ones behind.
- “Which epics are late?” A list of commitments that have already slipped.
- “How far along is PROJ-12?” For the one everyone is asking about.
If you want the number on the epic for everyone, not just in chat, see how to get an accurate epic progress bar in Jira.
When is a dashboard better than chat?
For a standing view, add the Tally — Epic Rollups dashboard gadget. With Group by it draws a To do / In progress / Done bar per group; without grouping, a % done chart for the least-done issues. Both charts are free. Standard adds a story points done vs remaining chart per group, see how to roll up story points to an epic. You can also sort in JQL, for example issuetype = Epic AND tallyPercent < 50 ORDER BY tallyPercent.
Tally’s panel, gadget and admin page are available in English, German, French and Spanish and follow each person’s Jira language; Rovo answers stay in English.
The takeaway
“Are we on track?” is a question about the whole tree under an epic. Give Rovo a rollup that counts every level, and the answer becomes a number you can check on the issue. Tally adds that rollup and the agent on its free plan; to compare options, see the best Jira epic progress apps.
Frequently asked questions
- Can Rovo tell me how far along a Jira epic is?
- Rovo can read the epic and list its child issues, but Jira doesn't store a % done that includes sub-tasks, so any figure Rovo works out itself is hard to check. An agent that reads a stored rollup, such as Tally Progress, returns % done and done / in progress / to do through every level.
- Does Jira's epic progress bar include sub-tasks?
- No. Jira's epic progress counts the epic's direct child issues by status category. Sub-tasks under stories don't count, so an epic can look further along than it is.
- Which Atlassian plans include Rovo?
- Atlassian includes Rovo credits in paid Jira Cloud plans (Standard, Premium and Enterprise). Free plans don't include it.
- Can the agent find late epics on the free plan?
- Yes, it finds epics past their due date that aren't done. Standard adds the check for epics whose children are due after the epic, plus story points and time. Teams of up to 10 users get Standard free too, and larger teams get a 30-day trial.
- Is there an app that answers epic progress questions in Rovo?
- Yes. Tally adds the Tally Progress agent. Ask "How far along is PROJ-12?", "Which epics in PROJ are least done?" or "Which epics are late?".