How to see percent complete on a Jira epic

Updated October 8, 2026

An epic with a dozen stories tells you almost nothing at a glance — it just says “In Progress” while the work underneath it moves. Jira knows every child’s state; it just never turns that into a percent complete. Here’s how to get one.

What Jira shows natively

Open an epic and Jira gives you its child issues, their statuses, and a basic progress bar in the Child issues panel — done vs. total direct children, by count. What it doesn’t give you:

  • A percentage number. The bar is visual; nothing labels it “67% complete.”
  • Rolled-up story points or estimates. Jira keeps points per issue and never totals a parent’s children, so the bar can’t be weighted by size — only a company-managed Scrum board’s Backlog panel can do that, and only in its sidebar.
  • Sub-tasks in the count. Only direct children show up; sub-tasks under those stories are invisible to it.

So “how far along is this epic?” stays a rough glance at an unlabeled bar — or a manual tally of the child list.

How to compute it

  • Pick a definition. By status (children done ÷ total) is the simplest and needs no estimates. By effort (story points or estimate done ÷ total) reflects that a 13-point story isn’t a 1-point one.
  • Include the whole tree. Sub-tasks under stories count too, so a real figure rolls up epic → story → sub-task, not just the epic’s direct children.
  • Put the number where it’s read. A percentage is only useful if it’s on the epic (and parent) issue, visible the moment someone opens it — see how to show sub-task progress on the parent issue.

Without a spreadsheet

Tally rolls children and sub-tasks up to the parent and epic, on the issue, with no formulas. Its free tier shows child status and a done/total count at a glance; its Standard tier rolls up story points, estimates and percent complete across the whole epic → story → sub-task tree. For the points side specifically, see how to roll up story points to an epic in Jira.

The takeaway

Jira shows an epic’s children but never a percentage, so progress is something you count by hand. Decide whether “complete” means status or effort, roll the whole tree up to the epic, and put the number on the issue — then epic progress becomes a figure you can read at a glance instead of infer.

Frequently asked questions

Does Jira show percent complete on an epic?
Not as a number. The epic's Child issues panel shows a basic progress bar — done vs. total direct children, by count — but no percentage label, no story-point weighting, and no sub-tasks. You either eyeball it from the bar or roll it up with an app.
How is epic percent complete calculated?
Usually one of two ways — by status (children done ÷ total children) or by effort (story points or estimate done ÷ total). Counting by status is simplest; weighting by story points reflects how big each child is.
Can I roll up story points to the epic to get a percentage?
Not on the issue itself — Jira keeps story points per issue and doesn't total a parent's children there. (A company-managed Scrum board's Backlog panel can show a points-weighted bar if its Estimation Statistic is set to Story Points, but that's sidebar-only.) A rollup app sums the children's points and shows percent complete directly on the parent and the epic.
Doesn't Advanced Roadmaps (now called Plans) show epic progress?
Plans (Jira Premium, formerly Advanced Roadmaps) shows a progress bar on the timeline — by points if you want — but not a percent figure on the epic issue itself, where your team actually looks.